| EPC-REQ-001 | Guaranteed net electrical output shall be at least 1,170 MW at the specified cooling water temperature of +15°C. | 1.0 (Contract) | In force | EPC Contract · Schedule 1 (Performance Guarantees) |
| EPC-REQ-002 | Unit capacity factor shall be at least 90% throughout the two-year warranty period. | 1.0 (Contract) | In force | EPC Contract · Schedule 1 (Performance Guarantees) |
| EPC-REQ-003 | The design service life of major non-replaceable equipment (reactor pressure vessel, steam generators and pressurizer) shall be at least 60 years. | 1.0 (Contract) | In force | EPC Contract · Schedule 2 (Critical Equipment Specification) |
| EPC-REQ-004 | Provide the complete construction and acceptance documentation electronically in the engineering information system, with verified links to the 3D model, before commissioning begins. | 2.0 (Contract) | In force | EPC Contract · Schedule 4 (Information Model and Engineering Information Management Requirements) |
| EPC-REQ-005 | Perform receiving inspection on all safety class 1, 2 and 3 equipment, issue FA-1 acceptance records and register them in Rebario PLM. | 1.0 (Contract) | In force | EPC Contract · Schedule 6 (Supply Quality Assurance Programme) |
| EPC-REQ-006 | Meet the contract milestone schedule, including primary circuit hydrostatic testing and initial reactor criticality by the specified dates. | 1.2 (Contract) | In force | EPC Contract · Schedule 7 (Construction Milestone Schedule) |