Engineering Document Register

Unit 1All design stages
Total documents
1,247
Approved
1,024
82.1%
Under review
38
Average turnaround: 6.4 days
In development
185
Actions
NR-NPP-001-TPNuclear plant design basis reportTPApproved303A2024-03-12D. I. Smirnov
NR-NPP-002-WDReactor Building process flow diagramWDApproved504B2024-04-25E. V. Petrova
NR-NPP-003-DDVVER-1200 reactor pressure vessel assembly drawingDDUnder review202A2024-03-05M. A. Kozlov
NR-NPP-004-ODPGV-1000M steam generator operating manualODApproved403C2024-01-18A. S. Ivanov
NR-NPP-005-PEUnit 1 construction cost estimatePEIn development101A2024-02-21O. P. Sokolova
NR-NPP-006-TPContainment structural calculationsTPApproved605A2024-05-10D. I. Smirnov
NR-NPP-007-WDEmergency core cooling system (ECCS) diagramWDApproved303A2024-06-14E. V. Petrova
NR-NPP-008-DDGCNA-1391 reactor coolant pump drawingDDUnder review202B2024-04-03M. A. Kozlov
NR-NPP-009-ODK-1200-6.8/50 turbine installation instructionsODIn development101A2024-05-28A. S. Ivanov
NR-NPP-010-WD6 kV station auxiliary power supply diagramWDApproved403B2024-07-02A. S. Fedorov
NR-NPP-011-TPSafety Analysis Report (SAR), Chapter 15TPUnder review706A2024-07-19D. I. Smirnov
NR-NPP-012-DDKD-79 pressurizer drawingDDWithdrawn101A2024-01-11M. A. Kozlov
NR-NPP-013-WDControlled area ventilation system diagramWDIn development202A2024-08-08E. V. Petrova
NR-NPP-014-ODOperational quality assurance programmeODApproved202A2024-08-22M. V. Sidorova
Showing 14 of 1,247
NR-NPP-003-DD

VVER-1200 reactor pressure vessel assembly drawing

Under reviewDetailed Engineering

Attributes

Reference
NR-NPP-003-DD
Current version
2 / 02A
Issue date
2024-03-05
Author
M. A. Kozlov
Asset
Unit 1
KKS tag
10UJA
Format
PDF

Review and approval workflow

  1. AuthorM. A. Kozlov
    Approved
  2. Standards reviewM. V. Sidorova
    Approved
  3. Project Chief EngineerA. P. Ivanov
    Pending